Froedtert Hospital Blue Parking Structure

  • Mar 31
  • 2 min read

Location: Milwaukee, Wisconsin

Award: High Performance


Project Team

Owner: Froedtert Hospital

Contractor: CG Schmidt

Architect: EUA – Milwaukee

Engineer: Graef

Concrete: Riv/Crete Ready Mix

Slag Cement: St Marys Cement



 Located in Milwaukee, Wisconsin, the Froedtert Hospital Blue Parking Structure is a five-story facility providing 2,400 parking spaces designed to enhance the experience for patients, visitors, and staff. This thoughtful design includes a climate-controlled pedestrian bridge, accessible parking near elevators, and critical safety and sustainability features.

For a massive post-tensioned structure like this, the construction schedule lived and died by early strength gain. The team utilized a slag cement replacement rate that was specifically optimized to hit 3,000 psi in just 20 hours. This allowed for a rapid and consistent post-tensioning sequence, ensuring the project stayed on track while still comfortably exceeding the 28-day requirement of 6,000 psi.

Slag cement was the clear choice over other supplementary materials because of its remarkable consistency. Even with a complex chemical cocktail of admixtures, including corrosion inhibitors and viscosity modifiers, the slag-based mix remained stable and predictable. This reliability was crucial for the team as they used maturity meters to time their post-tensioning across variable weather conditions over the multi-year build.

The thixotropic properties of the slag mix also improved pumpability, which was essential for a project that occasionally required multiple pump stages to reach the upper levels. By reducing permeability and ensuring consistent air entrainment, slag cement has provided the foundation for a structure designed with a 75-year service life. The Froedtert Blue Parking structure stands as a premier example of how slag cement delivers the precision and durability required for high-stakes healthcare infrastructure.


Application Type

Application Type

Slab mix

Exterior Columns & Shear Walls

% Slag Cement Replacement

15

10

% Portland Cement



% Portland Limestone Cement

85

80

% Other SCM (if applicable)

Carbon Cure; VMA, CI, Super, Mid-Range, AE, Hyd. Stab.

Fly Ash (10)

Aggregate

Combined Aggregate: ¾ gravel, 3/8 pea stone & sand; for pumpability & workability

Combined Aggregate: ¾ gravel, 3/8 pea stone & sand; for pumpability

Water/cement ratio

0.38 typ (max 0.4 per ACI F3)

0.40

7-day strengths

5700 psi, 3000 psi @ 20hr for PT

5200 psi

28-day strengths

6000 psi required, 7300 psi typical

5000 psi required, 6500 typical


1 Comment


Mình có lần lướt đọc mấy trao đổi trên mạng شيخ روحاني thì thấy nhắc nên cũng tò mò mở ra xem thử cho biết. Mình không tìm hiểu sâu جلب الحبيب chỉ xem qua trong thời gian ngắn để quan sát bố cục جلب الحبيب cách sắp xếp شيخ روحاني các mục và trình bày nội شيخ روحاني dung tổng thể. Cảm giác là các phần được trình bày khá gọn, các Berlinintim mục rõ ràng nên đọc lướt cũng không bị rối جلب الحبيب với mình như Berlinintim vậy là đủ để nắm tin cơ bản rồi. جلب الحبيب

,

,